Future Work

Next steps in the project

Work on properties of non-Port public jurisdictions—Washington State Department of Transportation (WSDOT), Seattle Public Utilities, Highline Public Schools, Burien, SeaTac, Des Moines—is scheduled to begin in 2017/2018. Work on residential and commercial properties is scheduled to begin in 2018/2019. Additional environmental review, including public outreach and a comment period, will occur before any work ensues on non-Port public jurisdictions, residential and commercial properties.

Most of the obstructions being removed and replaced are located on Port- and WSDOT-owned property, as summarized on the following graph and chart:

Obstruction Removal Summaries

 

Obstruction Removal Summary Statistics
Jurisdiction Obstruction Removal Understory Removal Total Obstructions to be Removed
Property Ownership Existing Obstructions1 Potential Obstructions2 Total Obstructions
City of SeaTac
Port 362 478 840 327 1,167
WSDOT 484 119 603 621 1,224
Public 87 41 128 0 128
Residential 46 22 68 0 68
Commercial/Religious 22 22 44 0 44
Subtotal 1,001 682 1,683 948 2,631
City of Burien
Public 6 0 6 0 6
Residential 58 14 72 0 72
Commercial 0 0 0 0 0
Subtotal 64 14 78 0 78
City of Des Moines
Public 0 0 0 0 0
Residential 16 22 38 0 38
Commercial 0 0 0 0 0
Subtotal 16 22 38 0 38
Totals 1,081 718 1,799 948 2,747

Notes:
Based on upcoming field verification work, all obstruction numbers are subject to change.
1. Existing obstructions are trees that are currently within the navigable airspace for STIA.
2. Potential obstructions are trees that are predicted to enter the navigable airspace within 5 years.

 

Timeline


Maps of Future Work

2017/2018 – Washington State Department of Transportation Properties

2017/2018 – Other Jurisdiction Properties

2018/2019 – Residential and Commercial Properties